Integral Clients - The Dorchester Hotel

Scope of Work: The project involved the removal of asbestos insulation residue from ceiling and walls within the ceiling void as part of the planned kitchen and staff canteen refurbishment. The working areas were completely soft stripped to ensure all asbestos was completely removed.

The project was carried out whilst the building remained in full operation. The works involved building directly connected modular hygiene units to the working areas in the basement and phased removal of all waste out of the building.

Project: Dorchester Hotel, 53 Park Lane, London, W1K 1QA
Client: The Dorchester Collection
Date & duration: July – August 2022 – 4 weeks
Number of operatives: 4-6